Detour Routes         Closures 

Schedule Updates:

Please Note: Updated 3/17/2023

March 17, 2023
 

2nd Street and County Line Road will be reopening at the end of day Saturday, March 18th. Due to weather forecast, closure of 5th Street and County Line Road will now be delayed to Thursday March 23rd.

 

Roadway Engineering will do its best to minimize disruption caused by construction. A company representative, wearing a safety vest will be present on the job site each day to answer questions or provide assistance as needed. If you cannot locate the company representative, please contact Project Inspector Brian McDuffie, with TKE Engineering at (951) 205-4454.

 

For up to date information regarding the project please visit www.CLRProject.com or http://www.cityofcalimesa.net/. If you have any questions or issues you would like to have addressed, please feel free to join us at the City of Calimesa City Hall Mondays at 11:30 .M to have your questions answered.

 

Thank you for your patience and cooperation as we work on constructing the County Line Road Roundabouts for the Cities of Calimesa and Yucaipa. Please remember that Businesses in the area remain OPEN during construction activities

March 7, 2023
 

With ongoing construction for the roundabout at the County Line Road and 2nd Street Street intersection, Base Pavement is scheduled to be placed on March 14th, and the closure is expected to reopen the week of March 20th. Roadway Engineering will be returning to the intersection to complete remaining work with daily temporary closures if needed.

 

The construction of the roundabout at the intersection of County Line Road and 5th  Street will occur next. This closure and construction at the intersection is expected to last between 8-12 weeks starting on March 20th. Normal working hours will be between 7:00 A.M and 4:00 P.M. Monday through Friday.

Roadway Engineering will do its best to minimize disruption caused by construction. A company representative, wearing a safety vest will be present on the job site each day to answer questions or provide assistance as needed. If you cannot locate the company representative, please contact Project Inspector Brian McDuffie, with TKE Engineering at (951) 205-4454.

 

For up to date information regarding the project please visit www.CLRProject.com or http://www.cityofcalimesa.net/. If you have any questions or issues you would like to have addressed, please feel free to join us at the City of Calimesa City Hall Mondays at 11:30 A.M. to have your questions answered.

 

Thank you for your patience and cooperation as we work on constructing the County Line Road Roundabouts for the Cities of Calimesa and Yucaipa. Please remember that Businesses in the area remain OPEN during construction activities.

February 17, 2023

This upcoming Monday, February 20th is President’s Day and the City of Calimesa City Hall will be closed. Therefore, Monday’s Residents meeting will be canceled. If you have any questions or concerns that require immediate attention, a company representative, wearing a safety vest will be present on the job site each day to answer questions or provide assistance as needed.

December 27, 2022

Roadway Engineering will be assisting the Department of Water Resources exploring underground utilities along the South bound lane of Bryant Street just north of County Line Road. The work is scheduled to be performed Wednesday, December 28th. Therefore, Southbound traffic will be closed for the day on Bryant Street and County Line Road intersection for Through Traffic. Detour signs will be placed at Avenue H directing South bound traffic to utilize Douglas Street. Roadway Engineering will do its best to minimize disruption caused by construction. A company representative, wearing a safety vest will be present on the job site each day to answer questions or provide assistance as needed.

December 9, 2022
 

With ongoing construction for the roundabout at the County Line Road and California Street intersection, Base Pavement is scheduled to be placed the week of December 19th and the closure is expected to reopen the last week of December. Roadway Engineering will be returning to the intersection to complete remaining work with daily temporary closures if needed.

 

The construction of the roundabout at the intersection of County Line Road and 2nd Street will occur next. This closure and construction at the intersection is expected to last between 5-7 weeks. Normal working hours will be between 7:00 A.M and 4:00 P.M. Monday through Friday.

Roadway Engineering will do its best to minimize disruption caused by construction. A company representative, wearing a safety vest will be present on the job site each day to answer questions or provide assistance as needed. If you cannot locate the company representative, please contact Project Inspector Brian McDuffie, with TKE Engineering at (951) 205-4454.

 

Please fine the following detour plan for upcoming closure at 2nd Street for your reference.

 

For up to date information regarding the project please visit www.CLRProject.com or http://www.cityofcalimesa.net/. If you have any questions or issues you would like to have addressed, please feel free to join us at the City of Calimesa City Hall Mondays at 11:30 .M to have your questions answered.

 

Thank you for your patience and cooperation as we work on constructing the County Line Road Roundabout for the Cities of Calimesa and Yucaipa.

Detour Route and Closures - 2nd Street.jpg

November 22, 2022

Happy Thanksgiving Calimesa and Yucaipa Residents. Construction along County Line Road will be paused for this Thursday and Friday, November 24th – 25th for Thanksgiving. Enjoy the holiday with your friends and family.

November 2, 2022
Public Residents’ Meeting scheduled for Monday, November 7th will be canceled. The City of Calimesa will be holding a Voting Assistance Center for the General Elections. If you have any questions or concerns which require immediate assistance, a company representative, wearing a safety vest will be present on the job site each day to answer questions or provide assistance as needed.

 
If you cannot locate the company representative, please contact Rafael Gomez at (714) 716- 6364 between 7:00 A.M. and 5:00 P.M. or Project Inspector Brian McDuffie, with TKE Engineering, Inc. at (951) 205–4454 between 7:00 A.M. and 5:00 P.M. For up to date information regarding the project please visit www.CLRProject.com or http://www.cityofcalimesa.net .

October 28, 2022
Bryant Street intersection is scheduled to reopen at the end of day Monday, October 10th. Roadway Engineering will be working this Saturday, October 8th between the hours of 10:00am and 5:00pm to perform final cleanup of the project site prior to reopening intersection. Roadway Engineering will do its best to minimize disruption caused by construction. A company representative, wearing a safety vest will be present on the job site each day to answer questions or provide assistance as needed. If you cannot locate the company representative, please contact Project Inspector Brian McDuffie, with TKE Engineering at (951) 205-4454.

October 25, 2022
Roadway is scheduled to perform street pulverization at County Line Road and California Street on Thursday and Friday, November 2nd and 3rd. Normal working hours are between 7:00 A.M. and 4:00 P.M. Monday through Friday. There will be an increase in dust, noise and limited street access due to pulverization.

 
You will receive additional information from Roadway if your house , business or driveway will be directly affected by the work. Roadway will do its best to minimize disruption caused by construction.
 
A company representative, wearing a safety vest will be present on the job site each day to answer questions or provide assistance as needed.
 
If you cannot locate the company representative, please contact Rafael Gomez at (714) 716- 6364 between 7:00 A.M. and 5:00 P.M. or Project Inspector Brian McDuffie, with TKE Engineering, Inc. at (951) 205–4454 between 7:00 A.M. and 5:00 P.M. For up to date information regarding the project please visit www.CLRProject.com or http://www.cityofcalimesa.net

October 5, 2022
Bryant Street intersection is scheduled to reopen at the end of day Monday, October 10th. Roadway Engineering will be working this Saturday, October 8th between the hours of 10:00am and 5:00pm to perform final cleanup of the project site prior to reopening intersection. Roadway Engineering will do its best to minimize disruption caused by construction. A company representative, wearing a safety vest will be present on the job site each day to answer questions or provide assistance as needed. If you cannot locate the company representative, please contact Project Inspector Brian McDuffie, with TKE Engineering at (951) 205-4454.

DJI_0022.JPG

September 23, 2022

With upcoming closure of California Street and County Line Road taking place first week of October, please find the following Detour Plan for your reference.

Detour Route and Closures - California Street.jpg

September 20, 2022

In an effort to stay within the construction schedule to reopen Bryant Street closure, Roadway Engineering will be working this Saturday, September 24th, between 10:00am and 5:00pm. Roadway Engineering will do its best to minimize disruption caused by construction. A company representative, wearing a safety vest will be present on the job site each day to answer questions or provide assistance as needed. If you cannot locate the company representative, please contact Project Inspector Brian McDuffie, with TKE Engineering at (951) 205-4454.

September 20, 2022

With ongoing construction for the roundabout at the County Line Road and Bryant Street intersection, Base Pavement is scheduled to be placed at the end of the month and the closure is expected to reopen the first week of October. Roadway Engineering will be returning to the intersection to complete remaining work with daily temporary closures if needed.

 

The construction of the roundabout at the intersection of County Line Road and California Street will occur next. This closure and construction at the intersection is expected to last between 5-6 weeks. Normal working hours will be between 7:00 A.M and 4:00 P.M. Monday through Friday.

Roadway Engineering will do its best to minimize disruption caused by construction. A company representative, wearing a safety vest will be present on the job site each day to answer questions or provide assistance as needed. If you cannot locate the company representative, please contact Project Inspector Brian McDuffie, with TKE Engineering at (951) 205-4454.

 

For up to date information regarding the project please visit www.CLRProject.com or http://www.cityofcalimesa.net. If you have any questions or issues you would like to have addressed, please feel free to join us at the City of Calimesa City Hall Mondays at 11:30 .M to have your questions answered.

 

Thank you for your patience and cooperation as we work on constructing the County Line Road Roundabout for the Cities of Calimesa and Yucaipa.

August 25, 2022

City of calimesa.jpf
Picture2.jpg
Picture5.jpg
Picture4.jpg
Picture1.jpg
Picture3.jpg
Picture3.jpg
Picture1.jpg
Picture2.jpg

PARTICIPATING AGENCIES

Calimesa.jpg
Yucaipa.gif
bottom of page